Don’t Run Afoul Of The Truth In Negotiations Act (TINA)


“NATIONAL DEFENSE MAGAZINE’ By Michael Gwinn


“TINA is a procurement statute that requires contractors to provide information — known as cost or pricing data — when negotiating certain contracts or contract modifications. In simple terms, cost or pricing data is information a reasonable negotiator would want to know during negotiations.


Congress demands that contractors provide this information so that government procurement personnel will be on equal footing during price negotiations.”

_______________________________________________________________________________

“Imagine paying a contractor $20,000 to remodel a kitchen. Although you aren’t sure if you paid a fair price because you only received one bid, the contractor performed on time and to standard and you are pleased with the results.


Two weeks later, you go to the hardware store and discover that the remodel only cost the contractor $5,000, which is a 300 percent profit margin. Would you want some of that $15,000 back?


Uncle Sam would. That’s why businesses in the federal marketplace should be aware of the Truth in Negotiations Act, or TINA.


The act is a frequent issue for government contractors, and it will become more frequent with the recent increase in defective pricing audits.


If the contractor does not disclose cost or pricing data when it should have, the government can sue the contractor for the “overpayment” in what is known as a “defective pricing claim.”


So when does TINA apply? The act applies to contracts and subcontracts greater than $2 million or modifications to contracts where the changes add up to more than $2 million. The threshold for modifications is not the net change, but the total dollar change. A $1.5 million addition and a $1 million deletion is a $2.5 million change for TINA purposes.


TINA has four major exceptions, however, that allow contractors and subcontracts to avoid TINA’s disclosure requirements: bids that receive adequate price competition such as more than one competitive bidder; bids for contracts where the price is set by law or regulation such as utilities; contracts for commercial items; and where the head of the contracting activity has waived TINA for that procurement.


Subcontracts are exempt from TINA if the parent contract has an exception — unless the prime contract is exempt under a waiver. In that case, TINA will still apply to subcontractors unless another exception applies or they receive their own waiver. TINA can sneak up during solicitations or contract performance.


How does the government enforce TINA and what are the consequences? The enforcement process normally starts with an audit by a federal agency such as Defense Contract Audit Agency, Government Accountability Office, or an agency inspector general. The auditor will review the contractor’s documents for evidence or information that could have led to a lower price, such as vendor proposals, historical performance data, etc., and bring the information and a recommendation to the contracting officer’s attention in an official audit report.


Based on the auditor’s report, the contracting officer will determine whether they want to attempt to recover the overpayment in a legal action known as a defective pricing claim. The statute of limitations for defective pricing claims is six years from when the government knew or should have known about the defective pricing disclosure.


In order to win a defective pricing claim, the contracting officer will need to demonstrate the following points: the information in question fits the definition of cost or pricing data; accurate, complete, and current data existed and were reasonably available to the contractor before the date of agreement on the price; accurate, complete, and current data were not submitted or disclosed to the contracting officer or one of the authorized representatives of the contracting officer and that these individuals did not have actual knowledge of such data or its significance to the proposal; the government relied on the defective data in negotiating with the contractor; and, the government’s reliance on the defective data caused an increase in the contract price.


Finally, how can a business be protected from TINA liability?


There are a few general guidelines to prevent a defective pricing claim against a business.


First, understand the likelihood of whether TINA will apply to the contract and whether your business can meet the act’s disclosure requirements before negotiations begin.

Second, TINA allows the government and the contractor to agree on an earlier date to provide cost or pricing data. This allows the business to better align their disclosures with their business cycles and prevent the need for a last minute “sweep.”


Next, advocate for a TINA exception as early in the contracting process as possible, throughout any audit, and during discussions with the contracting officer. Once a contracting officer decides that an exception applies, the government cannot normally backtrack.


Then, if the government is considering a defective pricing claim, prove that the information fails the five-point test provided above.


Finally, understand the statute of limitations and appeals process if the contracting officer issues a final decision.”




ABOUT THE AUTHOR Michael Gwinn is an associate at the law firm of Arnold and Porter.